Klohn Crippen Berger Ltd.

Transportation Projects
Alex Fraser Bridge
Client: Ministry of Transportation

Location: New Westminster, British Columbia

This award-winning, six-lane, 830 m long cable-stayed crossing of the Fraser River was completed after 30 months of construction. Use of repetitive precast concrete deck modules resulted in capital costs 20% lower than earlier North American cable-stayed bridges. Extensive wind tunnel testing confirmed the aerodynamic viability of the economical steel plate girder. Earthquake design was refined using dynamic interaction computer analyses while sand islands, developed to protect the piers from ship impact, were modelled in a hydraulic laboratory. CBA Engineering (now Klohn Crippen Berger), in joint venture with Buckland & Taylor, provided complete engineering, model testing, construction inspection and contract administration services. This bridge won the Canadian Consulting Engineering Award of Excellence.

Services:
  • Pre-feasibility studies and pre-engineering
  • Detailed design
  • Construction inspection
  • Contract administration
  • Model testing
HOME | SITE MAP | FTP SERVER | CONTACT US
Copyright Klohn Crippen Berger Ltd. All Rights Reserved